Free Online PRINCE2 PRINCE2-Practitioner Practice Test

Prepare Your PRINCE2 PRINCE2-Practitioner Exam Questions with Free online PRINCE2-Practitioner Practice Test. Get Brilliant PRINCE2 Practitioner Exam Results with Valid PRINCE2 Practitioner Exam Dumps.

Page:    1 / 75      
Total 375 Questions | Updated On: May 13, 2024
Add To Cart
Question 1

The project’s change control approach states that PRINCE2’s recommended issue and change control procedure will be used. The senior user has requested that a new set of marketing materials and marketing channels be introduced to support the launch of the training course. The senior user has suggested that this should be managed informally. Where should the project manager record the issue, and why?


Answer: B
Question 2

The 'e-learning course' is being delivered by an external consultancy. The testing of the e-learning has been completed by ABC Company’s testers and some faults have been found that still need to be fixed. The team manager for the 'e-learning course' work package believes the faults can be fixed within existing work package tolerances and has raised a request for change with the project manager. Is this an appropriate action, and why?


Answer: C
Question 3

While preparing the Configuration Management Strategy, the Project Manager considered the options for change control. He decided to recommend a change budget of £250k, but was undecided on the Change Authority to recommend. Which option is an appropriate Change Authority for the Outsourcing project?


Answer: B
Question 4

Which 2 statements should be recorded under the Expected benefits heading? 


Answer: A,C
Question 5

In the PRINCE2 Quality review technique, who would most likely carry out the role of administrator: 


Answer: B
Page:    1 / 75      
Total 375 Questions | Updated On: May 13, 2024
Add To Cart

© Copyrights DumpsCertify 2024. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsCertify.