Free PMI PMI-RMP Exam Questions

Become PMI Certified with updated PMI-RMP exam questions and correct answers

Page:    1 / 89      
Total 445 Questions | Updated On: Apr 25, 2025
Add To Cart
Question 1

You are working with the project stakeholders to analyze and prioritize their requirements for the project. One of
the project requirements is to achieve a high-level of customer satisfaction for the project deliverable. What is
the danger in this project requirement?


Answer: B
Question 2

A project team member identifies, but does not document, a risk early in the project, because it is considered to
be trivial. This risk occurs later and negatively impacts the project.
What could the project manager do to avoid this situation?


Answer: A
Question 3

During project execution, the project team realizes that the power outlet for imported equipment is not compatible with the current customer's electrical infrastructure. This event was originally identified as a risk during earlier stages of the project and the associated risk response indicated a plan to purchase a new power adapter. Which project fund will be used to cover this cost?


Answer: D
Question 4

Which of the following documents is described in the statement below? "It is developed along with all processes
of the risk management. It contains the results of the qualitative risk analysis, quantitative risk analysis, and risk
response planning."


Answer: C
Question 5

A risk facilitator is creating an outline for the risk management plan. To ensure alignment with the project's objectives, and to develop and recommend the project's risk strategy, what should be referenced to create this?


Answer: A
Page:    1 / 89      
Total 445 Questions | Updated On: Apr 25, 2025
Add To Cart

© Copyrights DumpsCertify 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsCertify.