Free PMI PMI-PBA Exam Questions

Become PMI Certified with updated PMI-PBA exam questions and correct answers

Page:    1 / 41      
Total 205 Questions | Updated On: Jun 05, 2025
Add To Cart
Question 1

A business analyst has been assigned to ProjectY. After a requirements gathering session, the project
manager asks the business analyst to identify which requirements would be considered in scope and out of
scope, based on the business need.
What document should the business analyst use to determine the relationship of the requirement to the
business need?


Answer: C
Question 2

Two weeks prior to the delivery date, a customer changes the business requirements. What should the business analyst do?


Answer: D
Question 3

The project manager is beginning to prepare for a test readiness review with the customer. The project
manager knows that the customer will want a summary of requirements that have been rejected or
deferred. The project manager has requested that the business analyst provide a list of rejected and
deferred requirements.
What should the business analyst have done to complete this request?


Answer: B
Question 4

The business managers had clearly stated that the delivered website must simultaneously accommodate
millions of users around the globe. However, within the first week of the production launch, the website
crashes frequently.
This situation could have been averted if


Answer: A
Question 5

How can a business analyst show progressive iterations of product development to stakeholders after the requirements baseline has been approved?


Answer: B
Page:    1 / 41      
Total 205 Questions | Updated On: Jun 05, 2025
Add To Cart

© Copyrights DumpsCertify 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsCertify.