Free BCS ISEB-PM1 Exam Questions

Become BCS Certified with updated ISEB-PM1 exam questions and correct answers

Page:    1 / 127      
Total 631 Questions | Updated On: Jun 16, 2026
Add To Cart
Question 1

Which of the following is not a cost of non-conformance?


Answer: A
Question 2

Which of the following is a tool and technique for activity duration estimating?


Answer: A
Question 3

The PV is $1000, EV is $2000 and AC is $1500. What is CPI?


Answer: A
Question 4

Your project team has identified several potential risks on your current project that could have a significant impact if they occurred. The team examined the impact of the risks by keeping all the uncertain elements at their baseline values. What type of diagram will the team use to display this information?


Answer: B
Question 5

A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes 3 weeks, Activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and B must be completed before Activity C can start. Activity C requires 6 weeks to complete. Activities B, C, and D must be completed before Activity E can start. Activity E requires 2 weeks. Activity F takes 4 weeks and can start as soon as Activity C is completed. Activity E must be completed before Activity G starts. Activity G requires 3 weeks. Activities F and G must be completed for the project to be completed. Which activities have float available?


Answer: A
Page:    1 / 127      
Total 631 Questions | Updated On: Jun 16, 2026
Add To Cart

© Copyrights DumpsCertify 2026. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsCertify.