Free CMAA Construction-Manager Exam Questions

Become CMAA Certified with updated Construction-Manager exam questions and correct answers

Page:    1 / 14      
Total 66 Questions | Updated On: Mar 06, 2026
Add To Cart
Question 1

The contract documents normally require which party/parties to coordinate the transfer of spare parts and warranties to the owner?


Answer: A
Question 2

Which schedule process determines the earliest times that schedule activities can start and Finish, and the total project duration?


Answer: B
Question 3

A relatively new general contractor has executed three projects. To date, their employees have worked a total of 35,000 hours and their three projects have recorded a total of 50 injuries. What is their recordable case rate? 


Answer: D
Question 4

Which of the following contract types limits the potential incentive to increase profit through increasing contract costs?


Answer: C
Question 5

The general contractor on a $1.2 billion terminal at an airport finds out that, due to supply chain issues, there is a 60% risk that they will not be able to get steel onsite for 10 weeks. The late start date of steel installation is four weeks away. Such a delay would cost the owner $75,000 per week to recover. What is the expected monetary value of risk?


Answer: D
Page:    1 / 14      
Total 66 Questions | Updated On: Mar 06, 2026
Add To Cart

© Copyrights DumpsCertify 2026. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsCertify.