Free CIMA CIMAPRO19-P01-1-ENG Exam Questions

Become CIMA Certified with updated CIMAPRO19-P01-1-ENG exam questions and correct answers

Page:    1 / 53      
Total 261 Questions | Updated On: Jun 05, 2025
Add To Cart
Question 1

A company accountant is trying to determine the optimum production plan for the period using linear programming.
The accountant has correctly formulated the linear programming problem as follows:
Variables (products): x and y
Objective function: Maximise contribution, C = 10x + 15y
Material constraint: 4x + 6y 500 (kg)
Labour constraint: x + 2y 350 (hours)
Machine constraint: 10x + 4y 1,500 (hours)
x constraint: 50 x 200
y constraint: y 0
Which of the following statements is true?


Answer: D
Question 2

A company has budgeted to produce 5,000 units of Product B per month. The opening and closing inventories of Product B for next month are budgeted to be 400 units and 900 units respectively. The budgeted selling price and variable production costs per unit for Product B are as follows:

73
Total budgeted fixed production overheads are $29,500 per month. The company absorbs fixed production overheads on the basis of the budgeted number of units produced. The budgeted profit for Product B for next month, using absorption costing, is $20,700.
Prepare a marginal costing statement which shows the budgeted profit for Product B for next month.
What was the difference between the profit calculation using marginal costing and the profit calculation using absorption costing?


Answer: C
Question 3

RFT, an engineering company, has been asked to provide a quotation for a contract to build a new engine. The potential customer is not a current customer of RFT, but the directors of RFT are keen to try and win the contract as they believe that this may lead to more contracts in the future. As a result, they intend pricing the contract using relevant costs. The following information has been obtained from a two-hour meeting that the Production Director of RFT had with the potential customer. The Production Director is paid an annual salary equivalent to $1,200 per 8-hour day. 110 square meters of material A will be required. This is a material that is regularly used by RFT and there are 200 square meters currently in inventory. These were bought at a cost of $12 per square meter. They have a resale value of $10.50 per square meter and their current replacement cost is $12.50 per square meter. 30 liters of material B will be required. This material will have to be purchased for the contract because it is not otherwise used by RFT. The minimum order quantity from the supplier is 40 liters at a cost of $9 per liter. RFT does not expect to have any use for any of this material that remains after this contract is completed. 60 components will be required. These will be purchased from HY. The purchase price is $50 per component. A total of 235 direct labour hours will be required. The current wage rate for the appropriate grade of direct labour is $11 per hour. Currently RFT has 75 direct labour hours of spare capacity at this grade that is being paid under a guaranteed wage agreement. The additional hours would need to be obtained by either (i) overtime at a total cost of $14 per hour; or (ii) recruiting temporary staff at a cost of $12 per hour. However, if temporary staff are used they will not be as experienced as RFT's existing workers and will require 10 hours supervision by an existing supervisor who would be paid overtime at a cost of $18 per hour for this work. 25 machine hours will be required. The machine to be used is already leased for a weekly leasing cost of $600. It has a capacity of 40 hours per week. The machine has sufficient available capacity for the contract to be completed. The variable running cost of the machine is $7 per hour. The company absorbs its fixed overhead costs using an absorption rate of $20 per direct labour hour.
Select ALL the true statements.


Answer: A,C,D
Question 4

Which THREE of the following statements about different costing systems are correct?


Answer: A,B,C
Question 5

Explain how probability analysis could be used to assess the risk of the evaluated projects.
Select all the true statements.


Answer: A,B,C
Page:    1 / 53      
Total 261 Questions | Updated On: Jun 05, 2025
Add To Cart

© Copyrights DumpsCertify 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsCertify.