Free FIDIC CCM Exam Questions

Become FIDIC Certified with updated CCM exam questions and correct answers

Page:    1 / 21      
Total 101 Questions | Updated On: Jun 16, 2026
Add To Cart
Question 1

For the FIDIC Red Book (both editions), the Contractor is required to submit a progress report monthly. When does the Contractor's reporting requirement end?


Answer: D
Question 2

Which of the following cases will allow the Employer to claim under the Performance Security? [2017 Edition] (2 correct answers apply) Choose all of the correct answers (multiple possibilities).


Answer: A,E
Question 3

You are the Contract Manager for the Engineer in a hotel project using FIDIC Red Book (edition 1999). The Employer demands perfection in the project's design and construction quality. There are many Variations initiated by the Employer during construction. Which one of the following is NOT considered as a Variation?


Answer: A
Question 4

Which two of the following statements are correct regarding Dispute under the FIDIC Red, Yellow, and Silver Books (edition 2017)? Choose all of the correct answers (multiple possibilities)


Answer: A,B
Question 5

You are the Contract Manager for the Engineer in a hotel project using FIDIC Red Book (edition 1999). The Employer demands perfection in the project's design and construction quality. There are many Variations initiated by the Employer during construction. Which one of the following is NOT considered as a Variation?


Answer: A
Page:    1 / 21      
Total 101 Questions | Updated On: Jun 16, 2026
Add To Cart

© Copyrights DumpsCertify 2026. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsCertify.