Free FIDIC CCM Exam Questions

Become FIDIC Certified with updated CCM exam questions and correct answers

Page:    1 / 21      
Total 101 Questions | Updated On: Apr 27, 2026
Add To Cart
Question 1

Under FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the revised programme? Choose all of the correct answers (multiple possibilities) 


Answer: A,B
Question 2

For the FIDIC Red Book (both editions), the Contractor is required to submit a progress report monthly. When does the Contractor's reporting requirement end?


Answer: D
Question 3

The Employer has prepared a contract for a waste-to-energy project based on the FIDIC Yellow Book (edition 1999). You are preparing negotiations on behalf of one of the Subcontractors with the Contractor. The main Contractor will manage the design and build of the Works, whereby the Subcontractor will deliver critical systems regarding power generation and cooling. The Contractor intends to contract the main Contract backto-back with the Subcontractor. In the proposed back-to-back subcontract, the following amendment is proposed through Particular Conditions: "Sub-Clause 4.4. The following paragraph is added: The Subcontractor is required to scrutinize the Employer's Requirements in a manner identical to the obligations of the Contractor as stated in Sub-Clause 5.1 of the Main Contract. The Subcontractor will indemnify and hold harmless (up to the maximum liability of the Subcontractor) the Contractor with regard to any error, fault or other defect found in the Employer's Requirements, its items of reference or Contractor's design of the Works for the scope part for which Subcontractor is contracted." What is your advice to the Subcontractor (SC) in regard to entering this proposed subcontract?


Answer: C
Question 4

You are the new Contract Manager of the Contractor in a bridge project using FIDIC Yellow Book (edition 2017). The project had been suspended due to a material change in the Employer's financial arrangement. You have worked with your team to identify several failures of the Employer in carrying its obligations under the Contract. Which one of the following does NOT allow the Contractor to issue Notice to terminate the Contract?


Answer: C
Question 5

The Employer has prepared a contract for a waste-to-energy project based on the FIDIC Yellow Book (edition 1999). You are preparing negotiations on behalf of one of the Subcontractors with the Contractor. The main Contractor will manage the design and build of the Works, whereby the Subcontractor will deliver critical systems regarding power generation and cooling. The Contractor intends to contract the main Contract backto-back with the Subcontractor. In the proposed back-to-back subcontract, the following amendment is proposed through Particular Conditions: "Sub-Clause 4.4. The following paragraph is added: The Subcontractor is required to scrutinize the Employer's Requirements in a manner identical to the obligations of the Contractor as stated in Sub-Clause 5.1 of the Main Contract. The Subcontractor will indemnify and hold harmless (up to the maximum liability of the Subcontractor) the Contractor with regard to any error, fault or other defect found in the Employer's Requirements, its items of reference or Contractor's design of the Works for the scope part for which Subcontractor is contracted." What is your advice to the Subcontractor (SC) in regard to entering this proposed subcontract?


Answer: C
Page:    1 / 21      
Total 101 Questions | Updated On: Apr 27, 2026
Add To Cart

© Copyrights DumpsCertify 2026. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsCertify.