When presenting a product roadmap to an adaptive team, which form of communication is the most appropriate?
While working on a project the CEO of the company has inform you that he would like to terminate the project and have you work on a few project. What kind of influence does this best represents?
While working on a project with a budget of $5,000, the project manager has determined that the earned value on the project so far is $1,750. So far the project has spent $2,900. What should the project manager report the status of the budget as?
Based on detailed analysis, the developer found that the software development for a new feature will take 400 hours, plus or minus 2%. What type of estimate does this best describe?