Question 1

Red Industries has been creating products for their customers tor years using traditional ways of working up until recently, they have been doing very well However they are currently losing customers to small competitors working in an Agile manner What is the most likely reason that the smaller competitors are doing better? 


Answer: B
Question 2

You are a Scrum Master on a project creating an optical fiber cable network across the country. The project has reached the Create User Stories process. Which of the following is NOT an input to this process?


Answer: B
Question 3

The Scrum Master can help the Product Owner update business justification in the Project Vision statement
and ensure continuous value justification for projects by facilitating which of the following processes?
A) Conduct Daily Standup
B) Groom Prioritized Product Backlog
C) Retrospect Project
D) Sprint Deliverables


Answer: A
Question 4

A Scrum Master is teaching Agile estimation techniques using Story Points to a new team. A more
experienced member of the team argues that:
An estimate expressed in Story Points is useful for a shorter period of time than an estimate in Ideal Days.
Is this true and what is the reason?


Answer: B
Question 5

Your company has discovered that it takes more than high quality, low cost, and differentiation to excel. It also takes speed and flexibility. This calls for a different approach: you are aware that the current process is not delivering acceptable results. What would be the next activity after becoming aware?


Answer: C
Page:    1 / 46      
Total 230 Questions | Updated On: Jan 27, 2026
Add To Cart

© Copyrights DumpsCertify 2026. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsCertify.