Free AACE AACE-CCP Exam Questions

Become AACE Certified with updated AACE-CCP exam questions and correct answers

Page:    1 / 20      
Total 100 Questions | Updated On: Jun 03, 2025
Add To Cart
Question 1

Given the project's status, how many hours have been earned if 6,573 hours have been spent and the project is 55% complete, against a planned 60%?


Answer: D
Question 2

A major hospital is planning a significant expansion of its facilities over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded, and construction will begin three years after the award of the design contract. The hospital plans to incorporate new, cutting-edge medical equipment and technology, requiring an estimate to be developed to identify these costs without historical data.What information is needed to develop a Class 2 definitive estimate for the hospital's expansion project?


Answer: A
Question 3

____________ is the application of total resources ($-workers-supports) and activity durations of the logic diagram.


Answer: C
Question 4

____________ is the application of total resources ($-workers-supports) and activity durations of the logic diagram.


Answer: C
Question 5

In a manufacturing operation with the following annual cost structure, calculate the shutdown and break-even points as a percentage of total capacity.Fixed expenses: $5,203,440Variable expenses: $7,091,040Semi-variable expenses: $6,217,750Sales: $26,385,480Additional Information: Semi-variable expenses at zero production equal 30% of the expenses at full (100%) capacity.


Answer: C
Page:    1 / 20      
Total 100 Questions | Updated On: Jun 03, 2025
Add To Cart

© Copyrights DumpsCertify 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the DumpsCertify.